[ARCHIVED] ADDENDUM #2 - North South Connector Project - Phase 2

Public Notice Graphic

THE SHELBY COUNTY COMMISSION

NORTH-SOUTH CONNECTOR

PHASE 2

ADDENDUM NO. 2

 

TO: ALL PROSPECTIVE CONTRACTORS AND SUPPLIERS

 

The changes, modifications, clarifications and/or additions covered by and set forth in this

Addendum No. 2 shall become part and be incorporated in the Specifications, Contract

Documents, Bid Documents, and Plans for the above referenced project. The Contractor shall

include this Addendum as well as any previous and subsequent addenda that may be issued with

his proposal Bid Documents as indicating his receipt and acceptance of its terms, requirements,

and clarifications.

 

The Contractor shall also acknowledge receipt of this addendum on page BD-16 of the

Specifications-Contractual Documents.

 

GENERAL INFORMATION: The CSX Railroad Water Main Crossing Subsurface

Exploration Report is being provided for reference and is not part of the project contract

documents.

 

SPECIFICATIONS:

  1. Table of Contents Page 2 of 2

Revisions: Replace Horizontal Directional Drilling (HDD) with Boring and Jacking Page

S-52 and update Fencing to begin on S-55.

 

  1. Re: Page BD-11, Items 12 through 14a

Revision: Replace Pipe Line Crossing section with new Gas, Railroad and Road

Crossings section. Additional text required changes to the pagination. Revised pages

BD-11 - BD14 are included.

 

  1. Re: Page BD-16 Item #12

Revision: Replace Pipe Line Crossing with Gas Crossing #1

 

  1. Re: Page BD-17 Item #13

Revision: Replace Pipe Line Crossing #2 with Gas Crossing #2

 

  1. Re: Page BD-17 Item #14

Revision: Replace Pipe Line Crossing #3 with Railroad Crossing #1

 

  1. Re: Page BD-17, Add New Item #14A

Revision: Add New Item #14A, Road Crossing #1

 

  1. Re: Page S-52 Horizontal Directional Drilling

Revision: Replace Section 7 in its entirety with New Section 7 Boring and Jacking (S-52

– S54). Reduced text impacted the pagination for Section 8 Fencing; Section 8 now

begins on S-55.

 

DRAWINGS:

 

  1. Re: Sheet 7 Plan AND Profile

Revision: Lump Sum Connection #2 should read Lump Sum Connection #5 – see

snippet below.

 

 

SPECIAL PROVISIONS (Continued)

 

Consent of Surety, Release of Liens, and Payment of Debts and Claims .............................SP-15

Contractor’s Affidavit of Release of Liens, and Payment of Debts and Claims (Form) .......SP-16

Consent of Surety to Final Payment (Form) .........................................................................SP-17

Railroad Crossing Permit & Hwy 280 Crossing Permit ........................................................SP-18

 

GENERAL SPECIFICATIONS

 

Definition of Terms................................................................................................................G-1

Proposal Requirements and Conditions .................................................................................G-4

Award and Execution of Contract ..........................................................................................G-8

Scope of Work .......................................................................................................................G-10

Control of Work .....................................................................................................................G-12

Control of Materials ...............................................................................................................G-24

Legal Relations and Responsibilities to Public ......................................................................G-27

Prosecution and Progress .......................................................................................................G-38

Project Completion ................................................................................................................G-46

Warranty and Guarantees .......................................................................................................G-49

 

STANDARD SPECIFICATIONS

 

Sitework, Excavation, and Earthwork ...................................................................................S-1

Concrete .................................................................................................................................S-13

Pipe Materials ........................................................................................................................S-25

Installation of Pressure Pipe...................................................................................................S-38

Grassing .................................................................................................................................S-44

Pavement, Gravel, and Concrete Surfaces .............................................................................S-48

Boring and Jacking ................................................................................................................S-52

Fencing ...................................................................................................................................S-55

 

 

Exhibit A – CSX Railroad Crossing Permit

Exhibit B – Hwy 280 Crossing Permit

Additional Info...